History


The Town of Easton voted at the 2010 Annual Town Meeting to adopt the Easton Sewer District which is comprised of the five areas of highest need for wastewater treatment. Annual Town Meeting also voted to design and permit the North Easton Village Wastewater Collection System to provide sewer service to a portion of North Easton Village (this construction took place during 2013 and is now complete).  The Town of Easton’s Comprehensive Wastewater Management Plan (2004) identifies North Easton Village as the top ranked “needs area” and recommends a municipal sewer system due to the density of existing development, its location within the Aquifer Protection District and the high rate of septic failures.  The sewer treatment facility located in the redeveloped Ames Shovel Works complex provides Easton with the ability to provide sewer treatment capacity to portions of North Easton Village and is part of the Town’s initial step in creating a municipal sewer system.
 

For information and project updates on the ongoing North Easton Village Infrastructure Project, please click here.   

 

(Update: February 2014) Construction for the North Easton Village Sewer is substantially complete. This sewer system and Waste Water Treatment Facility is the first in Easton and will be expanded in accordance with the Comprehensive Wastewater Management Plans and updates listed below. 
 

Publications and Documents


Please note: Hard copies of the publications listed below are available for your review at the Planning & Community Development Department, 136 Elm St. N. Easton. Please see Pam Almeida, Principal Clerk, 2nd Fl., end of the hall.

 

  • Presentation: Final Betterment Assessments for the NEV Sewer District: August 18, 2014: Presentation available here.
    Secretary of Environmental and Energy Affairs - Certificate of the Easton Comprehensive Wastewater Management Plan FEIR Certificate June 9, 2014
    Phase IV Comprehensive Wastewater Management Plan FEIR (Final Environmental Impact Report)Phase IV/FEIR: April 2, 2014  [notice: large file 220 MB - recommended to download / right click "save as" rather than open in browser]
    Notice of Project Change - Phase One Waiver Request: December 12, 2013
  • Comprehensive Wastewater Management Plan FEIR Update Presentation: December 16, 2013
    Comprehensive Wastewater Management Plan DEIR Update Presentation: January 14, 2013
    Easton Sewer District Map
    as of 2014:
    Click here

 

Written comments regarding the Notice of Project Change can be directed to Jack Troidl, P.E. at jtroidl@woodardcurran.com or Woodard & Curran

980 Washington St., Suite 325, Dedham, MA 02026

 

Warrant for Annual Town Meeting May 17, 2010 approving the Easton Sewer District and funding for the design and permitting of the North Easton Village Wastewater Collection System (Articles 18, 19 & 20)

Warrant for Special Town Meeting April 5, 2010 approving the Ames Shovel Works Complex Treatment Facility Funding (Article 3)

 

Documents Available at the Ames Free Library:

The December 2012 CWMP/DEIR Report (Volume I & II)

Shelf Number: R 363.7284 COMP 2012 V. 1 & V. 2 (Noncirculating Reference)

 

December 2013 MEPA Notice of Project Change and Request for Phase One Waiver for Easton CWMP

Shelf Number: R 363.7284 MEPA 2012 (Noncirculating Reference)


All other documents related to the sewer district can be found on our Minutes on Demand page. Click on the link to the left and then click "Planning Department" followed by "Sewer District". All files are available at that location. 

For additional information please contact the Planning & Community Development Department at (508) 230-0630 or email sdanielson@easton.ma.us.